Question: Assignment 2- Network Diagram Consider the following project: Activity Predecessor Activity A - Duration Estimate 2 CA 3 DA 4 B 2 H EF E,F

Assignment 2- Network Diagram Consider the
Assignment 2- Network Diagram Consider the following project: Activity Predecessor Activity A - Duration Estimate 2 CA 3 DA 4 B 2 H EF E,F 2 5 HJ 2 a. Drawn an AON (activity on node) network diagram representing the project above. Show ES, EF, LS, LF, project duration, critical path. b. Identify all the paths of the network diagram and note how long they are. c. What is the shortest possible time it will take to complete this project? Draw the network diagram using a drawing program such as Smart Draw, Visio, Word, Excel, Paint, or any other drawing program of your choice. Embed (or screenshot) the diagram in Word, answer the questions above, and submit to Assignment dropbox

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!