Question: Network Diagram Consider the following project: Activity Predecessor Activity Duration Estimate A - 2 B A 2 C A 3 D A 4 E B
Network Diagram
Consider the following project:
| Activity | Predecessor Activity | Duration Estimate |
| A | - | 2 |
| B | A | 2 |
| C | A | 3 |
| D | A | 4 |
| E | B | 2 |
| F | C | 3 |
| G | D | 6 |
| H | E, F | 2 |
| I | E, F | 5 |
| J | G, I | 1 |
| K | H, J | 2 |
a. Drawn an AON (activity on node) network diagram representing the project above. Show ES, EF, LS, LF, project duration, critical path.
b. Identify all the paths of the network diagram and note how long they are.
c. What is the shortest possible time it will take to complete this project?
Draw the network diagram using a drawing program such as Smart Draw, Visio, Word, Excel, Paint, or any other drawing program of your choice. Embed (or screenshot) the diagram in Word, answer the questions above, and submit to Assignment dropbox.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts