Question: Assignment 2 ?Process Design A manager wants to assign tasks to workstations to achieve an hourly output rate of 3 4 ?units. Assume that the

 Assignment 2 ?Process Design A manager wants to assign tasks to
Assignment 2 ?Process Design
A manager wants to assign tasks to workstations to achieve an hourly output rate of 3 4 ?units.
Assume that the shop works 6 0 ?minutes per hour ( i . e . , ?no breaks ) . ( 1 0 ?points )
a . ?Assign the tasks shown in the above precedence network ( times are on the nodes and are in
minutes ) ?to workstations using the following heuristic rules: ( i ) ?"Assign the task with the most
followers." ( ii ) ?Tiebreaker: "Assign the task with the longest time." Complete the following table with
your answers ( Round the intermediate calculations and final answers to 2 ?decimal places. ) ( 8 )
b . ?What is the efficiency of this production system? ( Round the intermediate calculations to 2
decimal places. Round the final answer to 1 ?decimal place. ) ( 2 )
workstations to achieve an hourly output rate of 3 4 ?units. Assume

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!