Question: Assignment 2: Project Risk Management & Contingency Determination Overview: Sydney Metro project details as per Assignment 1. As part of the risk management team of
Assignment 2: Project Risk Management & Contingency Determination
Overview:
Sydney Metro project details as per Assignment 1. As part of the risk management team of XYZ Contractor, you are supporting the submission for a Design and Construct (D&C) Contract. You should undertake the required risk management and assessment activities for determination of the required cost and schedule contingency allowance for the defined scope of project below from a D&C contractor's perspective. You are required to research and find more details of this major project in order to successfully complete the assignment.
Option A: Victoria Cross Station
Details:
- 31m below groundlevel
- Construction at the station includes excavating two shafts, one will be used for future station entry and vertical access and the second shaft will become a future servicefacility.
- Shaft 1: $10m (-20%, +50%), 2 month (-10%,+100%)
- Shaft 2: $5m (-20%, +50%), 1 month (-10%,+100%)
- Excavation of shaft 2 will commence after completion of shaft1.
- 3 properties around the station need to be acquired in 6months.
- Property 1: $5m (-10%,+30%)
- Property 2: $2m (-5%,+20%)
- Property 3: $3m (-5%,+25%)
- If one owner can negotiate a higher price, the other owners will likely raise the prices too and viceversa.
- It's expected the acquisition of these properties will be completed prior toconstruction.
- Otherconcerns:
- Underground services (2 months delay and $2m-$3m-$8mcost)
- 2 months delay in completion ofacquisitions
- Wet weather and increase in non-working days, more than 30mm/day rain will cause 3 days non-working day duringexcavationOption
- B:Barangaroo Station
Details:
- 25m below groundlevel
- The construction site is usedfor:
- Launching the TBM under Sydney Harbour to the BluesPoint
- Retrieving the cutter heads and shields of the two tunnel boring machines that tunnel from the Marrickville divesite
- Excavation and construction of the future BarangarooStation
- Shaft 1: $20m (-20%, +50%), 6 month (-10%,+100%)
- 2 properties around the station need to be acquired in 8months.
- Property 1: $10m (-10%,+30%)
- Property 2: $5m (-5%,+20%)
- If one owner can negotiate a higher price, the other owner will likely raise the prices too and vice versa. No relationship between these properties and other properties at the Victoria Cross Station wasidentified.
- It's expected the acquisition of these properties will be completed prior toconstruction.
- Otherconcerns:
- Underground services (2 months delay and $1m-$2m-$6mcost)
- 3 months delay in completion ofacquisitions
- 2 months delay in launching theTBM
- Wet weather and increase in non-working days, more than 30mm/day rain will cause 3 days non-working day duringexcavation
Option C:Tunnels between two stations
Details:
- TBMs will be used to excavate 15.5 kilometers of new twin rail tunnels between Chatswood and Marrickville.
- Estimated cost of TBM: $500k (-10%,+30%)
- Tunneling cost: ($600k-$700k-$1b)/km, length3km
- Expected tunneling duration: 6 month (-1mth,+3mths)
- Sydney Metro City & Southwest needs fiveTBMs.
- OtherConcerns:
- Breakdown of TBM, very unlikely but if occurs, it may cause 1-2-4 months delay with the repair cost of$50k-$50k-$200k

\f