Question: Assignment 3 Construction of a Residential Complex Using the Activity-on-Node (AON) Method Company Y is a construction company that has been awarded a contract to

Assignment 3

Construction of a Residential Complex Using the Activity-on-Node (AON) Method

Company Y is a construction company that has been awarded a contract to build a residential complex. They aim to efficiently manage the project using the Activity-on-Node (AON) method in their Critical Path Method (CPM) analysis. The project involves multiple activities with interdependencies and strict timelines.

Project Details:

  • Construction of a residential complex comprising three apartment buildings
  • Key deliverables include site preparation, foundation construction, building erection, interior work, and landscaping
  • Project duration: 12 months

Activity-on-Node (AON) Diagram:

yaml

A: Site Preparation

/ \

/ \

B: Foundation C: Building Erection

Construction

\ /

\ /

D: Interior Work

|

E: Landscaping

Activity Descriptions and Duration Estimates:

A: Site Preparation (4 weeks)

  • Clear the site and prepare it for construction activities
  • Tasks: Clearing vegetation, leveling the ground, establishing temporary facilities

B: Foundation Construction (10 weeks)

  • Build the foundations for the apartment buildings
  • Tasks: Excavation, pouring concrete, reinforcing structures

C: Building Erection (18 weeks)

  • Construct the apartment buildings
  • Tasks: Structural framing, roofing, exterior finishing

D: Interior Work (20 weeks)

  • Complete the interior work of the apartments
  • Tasks: Plumbing, electrical installations, flooring, painting

E: Landscaping (6 weeks)

  • Complete the outdoor landscaping and beautification
  • Tasks: Planting trees, laying pathways, installing outdoor amenities

Project Constraints:

  • Building permits must be obtained before commencing construction activities.
  • Availability of construction materials and equipment must be considered for timely execution.
  • Construction work should adhere to local building codes and regulations.

AON Method Analysis:

  • Determine the dependencies and sequence of activities based on the AON diagram.
  • Calculate the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and total float for each activity.
  • Identify the critical path, which consists of activities with zero total float and determines the project's minimum duration.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!