Question: Assignment 3 : Earned Value Analysis Instructions Please read and follow the instructions carefully. Failure to do so will result in a penalty to the

Assignment 3: Earned Value Analysis
Instructions
Please read and follow the instructions carefully. Failure to do so will result in a penalty to the to the evaluation.
1. Provide a title page with the title of the assignment, your full name, student ID, George Brown email address and date.
2. Provide a summary page (separate and distinct from the any rough work).
a. The summary page must provide the final answer to each question ONLY. No calculations and/or rough work should be part of the summary page.
b. The answers must be clearly numbered and are aligned with the order of the questions presented below. The answer must be clearly visible / highlighted.
3. Provide an appendix with all rough work / calculations. You must show your work. IF you are using excel or word for your calculations, the file must be provided. You can attach a screenshot of the file page(s); however, you must also upload the original file as well. Clearly title each file with the name of the assignment AND your name (first / last).
4. Provide in the appendix all the relevant MS Project items (if applicable).
5. If the assignment is submitted without the rough work / calculations / xl file, a penalty will be applied to the final evaluation.
6. All files MUST be submitted within D2L. No emailed submissions will be accepted. This is not negotiable.
7. Late assignments will be assessed a point deduction (from the total points available) per day for every day late past the due date.
8. Please ensure all work completed is your own work. Plagiarism is not acceptable. If it is determined that the work submitted is not your own, a possible mark of 0 will be assigned.
9. Total marks (20 points):
a. Marks awarded for:
i. the completed questions (summary page)
ii. for the attached and completed work (rough work / calculations)
10. The assignment is worth 4.0% of your overall mark.
11. This assignment is to be completed and submitted individually.
Questions:
Question 1:
Given the following small project activity and 3-point duration estimate.
Draw the network diagram representing the project. Total Marks 8.
(Ensure you show the calculations for all activity estimates derived from the 3 estimates provided for each in your appendix. The summary page should only show the final network diagram.)
Question 2:
Using the project above and the following status information (below) at the end of day 14, calculate/determine the following:
Total 12 Marks (4 for the rough work AND the values for each answer as per below)
a) Total project PV (Planned Value)(2 marks)
b) Total project EV (Earned Value)(2 marks)
c) Total project AC (Actual Cost)(1 mark)
d) Project performance with respect to cost and schedule (1 mark)
e) Estimate at completion & how much more / less money is required to complete the project (1 mark)
f) Forecasted duration & how many more / less days are required to complete the project (1 mark)
Show all work!!! Similar approach to in-class examples. Ensure you draw the network diagram and then display the activities on a timeline to show which activities are scheduled before, during and after the status day @ day 14.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!