Question: Assignment Content 1 Assignment - Web exercise 1 The following table provides a description for the project Z . table [ [ Activity ,
Assignment Content
Assignment Web exercise
The following table provides a description for the project
tableActivityDuration,Predecessor,tableCost to crash by daytableMax days tocrashA$B$CA$DA$E$FD E$G$C$
What is the critical path of this project?
What is the duration of this project? before crashing
If your task is to crash this project by days, what is the most efficient cost of doing itJust input the number with no decimals or dollar signs
Suppose that the project duration that you have calculated in question before crashing is the expected duration of the project. Its variance of the critical path is days. The principal requires you to complete the project before the day If you finish later, you will incur a fine. What is the probability of receiving a fine?
Your manager wonders whether or not you should crash the project by days. If you do the variance of the project duration will remain the same. What is the probability that you will receive a fine? Based on your calculations in Q and Q would you recommend crashing the project?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock