The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash by 1 day Max days to crash A 5 $ 300 1 B 3 S 100 1 C 4 $ 100 1 D 3 $ 200 4 $ 400 2 $ 4 $ 3 $ E F G H A A B D, E E C 500 300 100 2 3 2 3 2 1. What is the critical path of this project? 2. What is the duration of this project? (before crashing) 3. If your task is to crash this project by 2 days, what is the most efficient cost of doing it? (Just input the number with no decimals or dollar signs) 4. Suppose that the project duration that you have calculated in question 2 (before crashing) is the expected duration of the project. Its variance of the critical path is 4 days. The principal requires you to complete the project before the day 15. If you finish later, you will incur a fine. What is the probability of receiving a fine? 5. Your manager wonders whether or not you should crash the project by 2 days. If you do, the variance of the project duration will remain the same. What is the probability that you will receive a fine? Based on your calculations in Q4 and Q5, would you recommend crashing the project? The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash by 1 day Max days to crash A 5 $ 300 1 B 3 S 100 1 C 4 $ 100 1 D 3 $ 200 4 $ 400 2 $ 4 $ 3 $ E F G H A A B D, E E C 500 300 100 2 3 2 3 2 1. What is the critical path of this project? 2. What is the duration of this project? (before crashing) 3. If your task is to crash this project by 2 days, what is the most efficient cost of doing it? (Just input the number with no decimals or dollar signs) 4. Suppose that the project duration that you have calculated in question 2 (before crashing) is the expected duration of the project. Its variance of the critical path is 4 days. The principal requires you to complete the project before the day 15. If you finish later, you will incur a fine. What is the probability of receiving a fine? 5. Your manager wonders whether or not you should crash the project by 2 days. If you do, the variance of the project duration will remain the same. What is the probability that you will receive a fine? Based on your calculations in Q4 and Q5, would you recommend crashing the project?
Expert Answer:
Answer rating: 100% (QA)
Here re are the stepbystep calculations for each question 1 To find the critical path Start node is ... View the full answer
Related Book For
Physics for Scientists and Engineers A Strategic Approach with Modern Physics
ISBN: 978-0133942651
4th edition
Authors: Randall D. Knight
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The Centre for Information Technology at Provincial University has outgrown its office in Bates (B) Hall and is moving to Allen (A) Hall, which has more space. The move will take place during the...
-
The receiver most commonly used in AM and FM radio broadcast is the so-called superheterodyne receiver. Answer the following questions about this receiver. a. Draw the block diagram of a...
-
Suppose that f: R2 R2 has continuous first-order partial derivatives in some ball Br(x0, y0), r > 0. Prove that if Îf(x0, y0) 0, then and -afi / ay(x0, yo) afi ay afi/ax(xo. yo) af2
-
A note to a recent annual report issued by General Motors Corporation includes the following information: a. Does the company's use of three different inventory methods violate the accounting...
-
Review the threats and safeguards. For each threat in Figure 12-1: a. Give an example of how that threat could compromise IS, data, or IT at MRV. b. Is MRV particularly vulnerable to that threat...
-
The Ace Steel Mill estimates the demand for steel in millions of tons per year as follows: Millions of Tons Probability 10 ..................10 12 ..................25 14 ..................30 16...
-
Make sure to round for the final answer. 22. [-/1 Points] DETAILS TANAPMATH7 4.3.026. MY NOTES ASK YOUR TEACHER Jessica wants to accumulate $14,000 by the end of 6 years in a special bank account,...
-
A hollow, circular, cast-iron pipe (Ec = 12,000 ksi) supports a brass rod (Eb 14,000 ksi) and weight W = 2 kips, as shown. The outside diameter of the pipe is dc = 6 in. (a) If the allowable...
-
11. Freudian Slips and Gowns, Inc.'s income statement for 20XX is as follows: FREUDIAN SLIPS AND GOWNS Income Statement Contribution margin.. Less: Fixed costs Year Ended December 31, 20XX Sales...
-
Could you please check and send me the last results, because the system announced the wrong answer. Thanks Question 1 George was offered two options for a car he was purchasing: Lease option: Pay...
-
Context This task requires analysing a network scenario, design the network architecture and recommend IT solutions including ethical, security and sustainability considerations.The purpose of this...
-
What was the Prime Cost Percent for Mandy's BBQ Pit for August? Select one: a. 46.5% b. 73.9% c. 63.4% d. 85%
-
Finding Critical Values and Confidence Intervals. In Exercises 5-8, use the given information to find the number of degrees of freedom, the critical values x? and x*, and the confidence interval...
-
An investor sold 100 shares of ABC stock short at $25 and buys one ABC Jan 30 call @ $5. What is this investor's maximum gain, maximum loss, and breakeven points from this strategy?
-
Hi Tutor, could you help me with the above questions and show me your working/calculation (step by step). QUESTION 1 (35 MARKS) a) Find the future value of RM2,000 received today and deposited at...
-
Ann hires a nanny to watch her two children while she works at a local hospital. She pays the 19 year-old nanny $125 per week for 48 weeks during the current year. a. What is the employers portion of...
-
The four 1.0 g spheres shown in FIGURE P25.42 are released simultaneously and allowed to move away from each other. What is the speed of each sphere when they are very far apart? 10 nC 10 nC 1.0 cm...
-
Two positive point charges are 5.0 cm apart. If the electric potential energy is 72 J, what is the magnitude of the force between the two charges?
-
Two narrow slits 80 m apart are illuminated with light of wavelength 620 nm. What is the angle of the m = 3 bright fringe in radians? In degrees?
-
LO12 Identify and give examples of each of the three basic manufacturing cost categories.
-
CHOOSING BETWEEN CREDIT CARDS. Otis Hopkins recently graduated from college and is evaluating two credit cards. Card A has an annual fee of $75 and an interest rate of 9 percent. Card B has no annual...
-
PROTECTING AGAINST CREDIT CARD FRAUD. Wyatt Scott takes pride in managing his finances carefully with great attention to detail. He recently received a phone call in which he was asked to confirm his...
![Mobile App Logo](https://dsd5zvtm8ll6.cloudfront.net/includes/images/mobile/finalLogo.png)
Study smarter with the SolutionInn App