ASSIGNMENT
For a small project. use the traditional approach with a maximum daily resource sum limited to 10 units. Shift the highest resource rate first when a choice between two or more rates is needed. Identify the critical path.
\table[[Activity,\table[[Duration],[(days)]],\table[[Depends],[Upon]],\table[[Resource],[Rate]]],[A,2,-,0],[B,11,A,3],[C,3,A,4],[D,6,A,5],[E,4,C, D,6],[F,5,D,3],[G,3,E, F, H,1],[H,4,B, C,0]]