Question: Assignment Question 1 (50 points). The following project is at the end of its sixth week. Find the cost and schedule variances. Also, find the

Assignment

Question 1 (50 points).

The following project is at the end of its sixth week. Find the cost and schedule variances. Also, find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project. Comment on the project status.

Activity

Duration

Predecessor

Budget ($)

Actual Cost ($)

% Complete

A

2

None

300

400

100

B

3

None

200

180

100

C

2

A

250

300

100

D

5

A

600

400

20

E

4

B, C

400

200

20

Question 2 (50 points).

Resolve Question 1 above using the 50-50 rule for planned value and earned value. Comment on the project status.

Hint: The only thing that changes is the way earned value is calculated. Of course, everything that is calculated based on EV then also changes. Using the 50-50 rule, every activity that has finished continues to receive its full value while any activity that has started, but has not yet finished, receives 50 percent of its value.

PreviousNext

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!