Question: Assignment Questions for Module 3 A set of activities and their times (in days) are provided for a project along with their dependencies. The times

Assignment Questions for Module 3
A set of activities and their times (in days) are provided for a project along with their dependencies. The times are a=optimistic, b=pessimistic, and m=most likely.
ACTIVITY a m b Immediate Predecessor(s)
A 4.2 8.4 11.2 -
B 2.8 5.6 5.6 -
C 1.4 2.8 4.2 -
D 8.4 9.8 11.2 C
E 2.8 5.6 8.4 B,D
F 8.4 14 19.6 A,E
G 1.4 2.8 5.6 A,E
H 4.2 8.4 12.6 F
I 14 15.4 16.8 G
J 19.6 22.4 28 C
K 2.8 11.2 14 H,I
Calculate Expected Times of Completion for each activity.
Draw activity on node (AON) network diagram.
What is the Expected Time of Completion and the standard deviation of the project (based on AON diagram using critical path (CPM))?
Calculate Slack1 and Slack 2 for all activities of the project.
What is the probability of completing the project in 55 days?
Prepare a complete Gannt Chart for the project showing activities (based on time of completion for each and dependencies) and slack.
Note: Please answer the questions asked in the worksheet titled "Answers."

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!