Assignment You are the Project Manager and have been asked to prepare a project charter based on the following information:
Sponsor: Seneca College
Job: Seneca College wants the library at the North York Campus painted for the Winter semester
Time: 4 months (16 weeks)
Internal Expertise: Painters/Labourers Needed Expertise / Outsource: Plaster/Drywall
Work Budget: $50,000
Expected Costs: $42,000
Over runs: any expenses over $5,000 each project Manager must get approval from the Dean of Business
Issues / Risks: if lead paint is required approval from Ministry of Health required Unionized painters MUST be used Matte paint for walls Satin for ceiling
Approval: Final approval must be signed off by Dean of Business
Time Requirements: 1 week to empty library (furniture and wall fixtures) 2 weeks to scrape old paint off walls 3 weeks to fix damage (drywall/plaster) 2 weeks to prime 3 weeks to sand and patch 2 weeks to paint 1 week to place furniture and wall fixtures back in library 1 weeks to touch up 1 week to complete walkthrough
Sponsor Contact: David
Start Date: October 1st, 2021
Approval: 1 week before start time, colour approval
Acceptance: Paint review, no runs, pits, or scratches