Question: Assist in drawing the chart Activity Immediate Predecessors Normal Completion Time (Weeks) Crash Completion Time (Weeks) Normal Cost (Total) Crash Cost (Total) A -- 6
Assist in drawing the chart
| Activity | Immediate Predecessors | Normal Completion Time (Weeks) | Crash Completion Time (Weeks) | Normal Cost (Total) | Crash Cost (Total) |
| A | -- | 6 | 6 | $100 | $100 |
| B | A | 10 | 4 | $2,000 | $2,600 |
| C | A | 10 | 8 | $800 | $920 |
| D | B | 6 | 5 | $700 | $750 |
| E | B | 8 | 6 | $1,000 | $1,140 |
| F | C,D | 9 | 7 | $1,400 | $1,550 |
| G | E | 14 | 10 | $3,000 | $3,320 |
| H | E,F | 10 | 8 | $900 | $1,020 |
The Normal Cost for an activity is the total cost to complete that activity in the Normal Time and the Crash Cost is the total cost to complete that activity in the Crash Time.Use the Normal Times to answer parts a) through c).
a) Draw the project network.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
