Question: You are given the following network. Activity Immediate Predecessors Normal Completion Time (Weeks) Crash Completion Time (Weeks) Normal Cost (Total) Crash Cost (Total) A --

You are given the following network.

Activity Immediate Predecessors Normal Completion Time (Weeks) Crash Completion Time (Weeks)

Normal Cost (Total)

Crash Cost (Total)
A -- 6 6 $100 $100
B A 10 4 $2,000 $2,600
C A 10 8 $800 $920
D B 6 5 $700 $750
E B 8 6 $1,000 $1,140
F C,D 9 7 $1,400 $1,550
G E 14 10 $3,000 $3,320
H E,F 10 8 $900 $1,020

e) Now, for every week that the project is reduced, there is a $120 benefit. What is the minimum

cost schedule and what is the cost of the project considering the benefit received. Also identify which activities to crash and by how many weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!