Question: Assistance with critical path chart - last 4 columns are my first try - Confirm or offer corrections Task Time Immediate Predecessors Early Finish Late

Assistance with critical path chart - last 4 columns are my first try - Confirm or offer corrections

Task

Time

Immediate Predecessors

Early

Finish

Late

Finish

Slack

Critical

Path?

1

A

2

--

2

2

0

A

2

B

3

A

3

5

0

B

3

C

3

B

5

8

0

-

4

D

7

B

5

12

0

-

5

E

6

B

5

11

0

E

6

F

1

C, D

12

13

-5

-

7

G

5

D, E

11

16

0

G

8

H

4

F, G

13

17

1

-

9

I

8

G

16

25

0

I

10

K

2

H, I

25

27

0

K

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!