Question: Consider the network described in the table below. Optimistic 4 Immediate Activity Predecessor(s) Pessimistic J 19 K 9 L J 10 M J 3 N

Consider the network described in the table
Consider the network described in the table
Consider the network described in the table
Consider the network described in the table below. Optimistic 4 Immediate Activity Predecessor(s) Pessimistic J 19 K 9 L J 10 M J 3 N KM 9 O KM 10 P LN 10 7 5 Probable 10 8 6 3 5 7 8 3 1 4 3 a. Draw the network diagram and fill out the chart below (by doing the forward and backward path analysis). (8 pts) Early Start Early Finish Late Start Late Finish Slack Time Expected Task Time Variance J K L M N O P b. Write the critical path and calculate the expected duration and standard variance of the critical path. (4 pts) c. 1) Calculate the probability that the project will be completed in fewer than 30 time units. 2) How much time does it need to finish the project by 95% chance? (4pts) d. Draw the Gantt Chart for this problem. (4pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!