Question: Associate each EVM value to its source. Except for Cost at Completion, assume the reference is to items sometime midway through a project: Budget at
Associate each EVM value to its source. Except for Cost at Completion, assume the reference is to items sometime midway through a project:
Budget at Completion (BAC)
Actual Cost of Work Performed (ACWP)
Budgeted Cost of Work Scheduled (BCWS)
Estimate at Completion (EAC)
Budgeted Cost of Work Performed (BCWP)
Estimate to Complete (ETC)
Cost at Completion (CAC)
Schedule Variance (SV)
Source:
a. Estimates & Actuals
b. Actuals Only
c. Estimates Only