Question: Assume a company's activity - based costing system includes three activities. The following information is available with respect to those activities: table [ [
Assume a company's activitybased costing system includes three activities. The following information is available with respect to those activities:
tableEstimated,Activity Cost Pool,Overhead Cost,Expected ActivityTesting$ testing minutesSetups$ setup hoursMolding$ machine hours
What is the activity rate for the Setups activity?