Assume a project has three activities A,B and C are24,000OMR,30,000OMR and50,000OMR respectively. After13months during review, it is
Fantastic news! We've Found the answer you've been seeking!
Question:
Assume a project has three activities A, B and C are 24,000 OMR, 30,000 OMR and 50,000 OMR respectively. After 13 months during review, it is found that 18,000 OMR, 25,000 OMR and 44,000 OMR has been spent so far to complete 100%, 65% and 75% of the tasks.
By using Earned Value Management method, A, B&C.
(i) Estimate the amount to be spent to complete the project.
(ii) Estimate the time to complete the project?