Question: Assume an auditor is evaluating a statistical attribute sample of 50 items that results in three deviations. What should the auditor conclude if the tolerable
Assume an auditor is evaluating a statistical attribute sample of 50 items that results in three deviations. What should the auditor conclude if the tolerable deviation rate is 7 percent, the expected population deviation rate is 5 percent, and the allowance for sampling risk is 2 percent? In addition, explain why you chose the answer you did.
a. The planned assessed level of control risk should be modified because the tolerable deviation rate plus the allowance for sampling risk exceeds the expected population deviation rate.
b. The sample results should be accepted as support for the planned assessed level of control risk because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable deviation rate.
c. The sample results should be accepted as support for the planned assessed level of control risk because the tolerable deviation rate less the allowance for sampling risk equals the expected population deviation rate.
d. The planned assessed level of control risk should be modified because the sample deviation rate plus the allowance for sampling risk exceeds the tolerable deviation rate.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts