Question: Assume: Store 1 : Lead - Time Demand ( Throughput , R 1 ) is 1 , 0 0 0 units, Lead - Time -

Assume:
Store 1:
Lead-Time Demand (Throughput,R1) is 1,000 units,
Lead-Time-Demand Standard Deviation (STD 1) is 300 units,
Store 2:
Demand Rate (Throughput,R2) is 2,000 unit/day,
Demand Standard Deviation ({:STD2) is 400 units,
What is the combined Lead-Time-Standard-Deviation?
units
Combined STD = SQRT (STD12+STD22)=
SORT (300???+400?7)=500 units