Question: Assume that a job involves 2 activities ( x and y . and 3 resources ( A , B , & C ) . Resource

Assume that a job involves 2 activities (x and y. and 3 resources (A, B, & C). Resource A is busy for 10 minutes on activity x and is not used on activity y. Resource B is busy for 10 minutes on activity x and 10 minutes on activity y. Resource C is not used on activity x and is busy for 10 minutes on activity y. If 1 unit of each resource is available and multiple resources can work on a job at the same time and, 1 job is on the schedule the utilization of A, B, and C will be:
10/20,10/20, and 10/20
O 10/40,20/40, and 10/40
10/10,10/10, and 10/10
05+5+5+5 minutes