Question: Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $160/week. What would the fully
Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $160/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 190 hours at $11.50/hour?
2945
2399
None of the given Answers
5130
4038