Question: Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $150/week. What would the fully

Assume that overhead is charged on a flat-rate basis. Each member of the project is assigned an overhead charge of $150/week. What would the fully loaded cost of labor be for an employee, given that she is assigned to the project for 200 hours at $10.50/hour?