Time | Cashflow | DCF |
Year 0 | -1500 | ? |
Year 1 | 1000 | 869.57 |
Year 2 | 800 | 604.91 |
Year 3 | 700 | 460.26 |
Year 4 | 500 | 285.88 |
Calculate the PBP of the project.