Assume that the risk adjusted cost of capital is 16% for project A, 18% for project B,
Fantastic news! We've Found the answer you've been seeking!
Question:
- Assume that the risk adjusted cost of capital is 16% for project A, 18% for project B, and 20% for project C.
Project A: Estimated cash flow is $25,800 per year for 10 years.
Cost $100,000
Project B: Estimated cash flow is $33,500 per year for 8 years.
Cost $125,000
Project C: Estimated cash flow is $44,000 per year for 7 years.
Cost $155,000
A. Compute the Payback, NPV, IRR and Profitability Index for each.
B. Rank order the Projects according to the value to the firm
Related Book For
Fundamentals Of Corporate Finance
ISBN: 9780135811603
5th Edition
Authors: Jonathan Berk, Peter DeMarzo, Jarrad Harford
Posted Date: