Question: Assume the following for a project under evaluation: ** The project's life is 4 years. ** The total time zero, initial cost of $55,000. **
Assume the following for a project under evaluation:
** The project's life is 4 years.
** The total time zero, initial cost of $55,000.
** The total net operating cash flow each year is $15,000.
** In addition to the terminal year operating cash flow, there is a non-operating, terminal year cash flow of $8,000
If the cost of capital for a project of this risk is 7%, what is the project's NPV? Accept or reject the project?
| A | 123,000; accept | |
| B | 13,000; accept | |
| C | -56,911; reject | |
| D | 1,911; accept | |
| E | 13,355; accept |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
