Question: Assume the following Hamburger sandwich processes Order 20 second Bread 10 seconds Fill 40 seconds Toaster 30 seconds Wrap 5 seconds. The bottleneck time is:

Assume the following Hamburger sandwich processes

Order 20 second

Bread 10 seconds

Fill 40 seconds

Toaster 30 seconds

Wrap 5 seconds.

The bottleneck time is:

a.

40 seconds

b.

35 seconds

c.

20 seconds

d.

10 seconds