Question: Assume the network and data that follow: ACTIVITYNORMAL TIME ( WEEKS ) NORMAL COSTCRASH TIME ( WEEKS ) CRASH COSTIMMEDIATE PREDECESSORSA 2 $ 5 0
Assume the network and data that follow:
ACTIVITYNORMAL TIME WEEKSNORMAL COSTCRASH TIME WEEKSCRASH COSTIMMEDIATE PREDECESSORSA$$BACADAEBFDGC E F
b Indicate the critical path when normal activity times are used.
multiple choice
ABEG
ADEG
ADFG
ACFG
JOB AND DESCRIPTIONIMMEDIATE PREDECESSORSTIME
HOURSa Startb Get computer printouts of customer purchasesac Get stock records for the monthad Reconcile purchase printouts and stock recordsb, ce Total stock records by departmentb, cf Determine reorder quantities for coming periodeg Prepare stock reports for purchasing agentsd, fh Finishg
How long will the total process take?
Which jobs can be delayed without delaying the early start of any subsequent activity?
multiple choice
b and d
c and e
e and f
d and g
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock