Question: Assume the network and data that follow: ACTIVITYNORMAL TIME ( WEEKS ) NORMAL COSTCRASH TIME ( WEEKS ) CRASH COSTIMMEDIATE PREDECESSORSA 2 $ 5 0

Assume the network and data that follow:
ACTIVITYNORMAL TIME (WEEKS)NORMAL COSTCRASH TIME (WEEKS)CRASH COSTIMMEDIATE PREDECESSORSA2$501$70B4802160AC8704110AD660580AE71006130BF4403100DG51004150C, E, F
b. Indicate the critical path when normal activity times are used.
multiple choice 1
A-B-E-G
A-D-E-G
A-D-F-G
A-C-F-G
JOB AND DESCRIPTIONIMMEDIATE PREDECESSORSTIME
(HOURS)a. Start0b. Get computer printouts of customer purchasesa10c. Get stock records for the montha20d. Reconcile purchase printouts and stock recordsb, c30e. Total stock records by departmentb, c20f. Determine reorder quantities for coming periode40g. Prepare stock reports for purchasing agentsd, f20h. Finishg0
How long will the total process take?
Which jobs can be delayed without delaying the early start of any subsequent activity?
multiple choice
b and d
c and e
e and f
d and g

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!