Question: Assume the network and data that follow: IMMEDIATE PREDECESSORS ACTIVITY A B C D E F G NORMAL TIME NORMAL CRASH TIME (WEEKS) COST (WEEKS)



Assume the network and data that follow: IMMEDIATE PREDECESSORS ACTIVITY A B C D E F G NORMAL TIME NORMAL CRASH TIME (WEEKS) COST (WEEKS) 2 $ 50 1 4 80 2 8 70 4. 6 60 5 7 100 6 4 40 3 5 100 4 CRASH COST $ 70 160 110 80 130 100 150 A A A B D C, E, F Es.pl b. Indicate the critical path when normal activity times are used. O A-D-F-G .pd O A-B-E-G O A-C-F-G A-D-E-G dus ipke c. Demonstrate the crashing steps needed to minimize the cost of crashing down to various project lengths. Consider project lengths of 18, 17, 16, 15, 14, and 13 weeks. For each possible step down in project length, specify which activity would be crashed to achieve that length, compute the resultant length of each path in the project, and compute the crashing costs as shown in the table below. (Leave no cells blank - be certain to enter "O" wherever required.) Saveo Exit Submit c. Demonstrate the crashing steps needed to minimize the cost of crashing down to various project lengths. Consider project lengths of 18, 17, 16, 15, 14, and 13 weeks. For each possible step down in project length, specify which activity would be crashed to achieve that length, compute the resultant length of each path in the project, and compute the crashing costs as shown in the table below. (Leave no cells blank - be certain to enter "O" wherever required.) 18 Weeks 17 Weeks 16 Weeks 15 Weeks 14 Weeks 13 Weeks Project Duration: Length of path ABEG Length of path ACG Length of path ADFG Activity crashed Crash cost for this step Cumulative crash cost Total direct cost d-1. If the indirect costs for each project duration are $400 (18 weeks), $350 (17 weeks), $300 (16 weeks), $250 (15 weeks), $200 (14 weeks), and $150 (13 weeks), what is the total project cost for each duration? Duration Total Costs 18 Saved Help Save & Exit Submit d-1. If the indirect costs for each project duration are $400 (18 weeks), $350 (17 weeks), $300 (16 weeks), $250 (15 weeks), $200 (14 weeks), and $150 (13 weeks), what is the total project cost for each duration? Duration Total Costs 18 17 53 16 15 14 13 s d-2. Indicate the minimum total project cost duration. 14 or 15 weeks 16 or 15 weeks 17 weeks