Question: In order to crash the project given below by 4 days, what will be the minimum cost of crashing? IMMEDIATE PREDECESSOR(S) ACTIVITY A B C

In order to crash the project given below by 4

In order to crash the project given below by 4 days, what will be the minimum cost of crashing? IMMEDIATE PREDECESSOR(S) ACTIVITY A B C D E NORMAL CRASH TIME NORMAL TIME (DAYS) (DAYS) COST (5) 5 4 1000 7 5 400 3 2 600 4 2 1000 7 4 1100 ANNUT CRASH COST [t] 1200 600 800 1500 2000 A, B The minimum cost of crashing is t (enter your response as a WHOLE NUMBER)