Question: Assume the network and data that follow: table [ [ ACTIVITY , table [ [ NORMAL TIME ] , [ ( WEEKS )
Assume the network and data that follow:
tableACTIVITYtableNORMAL TIMEWEEKSNORMAL COST,tableCRASH TIMEWEEKSCRASH COST,tableIMMEDIATEPREDECESSORSA$BACADAEBFDGC E F
b Indicate the critical path when normal activity times are used.
ACFG
ADFG
ABEG
ADEG
c Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider durations of and weeks.
Note: Leave no cells blank be certain to enter O wherever required.
Answer is complete but not entirely correct.
tableProject Duration:, Weeks, Weeks, Weeks, Weeks, Weeks, WeeksLength of path ABEG,Length of path ACG,Length of path ADFG,Activity crashed,None,&