Question: Assume the network and data that follow: table [ [ ACTIVITY , table [ [ NORMAL TIME ] , [ ( WEEKS )

Assume the network and data that follow:
\table[[ACTIVITY,\table[[NORMAL TIME],[(WEEKS)]],NORMAL COST,\table[[CRASH TIME],[(WEEKS)]],CRASH COST,\table[[IMMEDIATE],[PREDECESSORS]]],[A,2,$50,1,70,-],[B,4,80,2,160,A],[C,8,70,4,110,A],[D,6,60,5,80,A],[E,7,100,6,130,B],[F,4,40,3,100,D],[G,5,100,4,150,C, E, F]]
b. Indicate the critical path when normal activity times are used.
A-C-F-G
A-D-F-G
A-B-E-G
A-D-E-G
c. Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider durations of 13,14,15,16,17, and 18 weeks.
Note: Leave no cells blank - be certain to enter "O" wherever required.
Answer is complete but not entirely correct.
\table[[Project Duration:,18 Weeks,17 Weeks,16 Weeks,15 Weeks,14 Weeks,13 Weeks],[Length of path ABEG,18vv,17vv,16,15vv,14vv,130],[Length of path ACG,150,14o.,14vv,14,15,130],[Length of path ADFG,17vv,16,16,15?,14,130],[Activity crashed,None,(),2,(,B&F,x,x
 Assume the network and data that follow: \table[[ACTIVITY,\table[[NORMAL TIME],[(WEEKS)]],NORMAL COST,\table[[CRASH TIME],[(WEEKS)]],CRASH

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!