Question: Assume the project data given in Table. Determine the Cost slope for each activity Calculate the normal direct costs of the project table [

Assume the project data given in Table.
Determine the Cost slope for each activity
Calculate the normal direct costs of the project
\table[[Activity,Predecessor,Normal,Crash,,Cost slope,],[Duration (day),Cost (JD),Duration (day),Cost(JD),],[A,-,52,1200,77,1400,,,],[B,A,23,1800,15,2800,,,],[C,A,45,1700,25,1900,,,],[D,B, C,35,1400,20,2000,,,]]