Question: Open with PROBLEM THREE (40 points) Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of

Open with PROBLEM THREE (40 points) Given: The table shown below, which lists the normal and crash durations, and costs for a project, comprising of seven activities, and the network diagram for said project. All durations are in days, and all costs are in dollars. The network diagram for the project is also shown below. Activity Immediate Normal Normal Crash Crash Predecessor Duration Cost Duration Cost ABCDEFC A 6 100 4 500 - 10 200 10 200 A 3 50 2 300 B, C D D G LU 4472 150 4 150 250 3 450 200 7 200 50 1 100 E B D F 4 Required: Determine a) The critical path; b) The normal duration and the normal cost of the project; and c) By how many days can this project be crashed, and at what cost