Question: Assume the table below defines the activities for a small project. Task Completion Time Dependencies ( days ) table [ [ A , 7

Assume the table below defines the activities for a small project.
Task
Completion Time Dependencies
(days)
\table[[A,7,-],[B,5,A],[C,4,B],[D,3,A],[E,3,D],[F,6,E]]
\table[[G,8,C, E],[H,6,F, G]]
a. Using the tasks and dependencies above, draw a Precedence Diagram Method (PDM)(i.e., Pert Chart) network diagram for the above project. Use SmartDraw or a similar drawing tool. You can also draw by hand.
b. A PDM Network Diagram is commonly used when applying the Critical Path Method to a project. Based on your diagram, what is the critical path for this project?
c. How many days will it take to complete the project if everything stays on schedule?
d. How many days can task D be delayed (if any) without causing the overall project to go off schedule?
 Assume the table below defines the activities for a small project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!