Question: The table below defines the activities within a small project Activity Completion time Immediate predecessor (weeks) activities ABCDEFGH 5 7 6 34265 A B,C C
The table below defines the activities within a small project Draw the AON network diagram and perform the forward path calculations, answer the following questions: - What is the project duration? [ Select ] - What is the earliest start time for activity G? - What is the earliest finish time for activity B