Question: Assume the time used for each activity is the expected time required to finish that activity, and the project completion time calculated in part 4

Assume the time used for each activity is the expected time required to finish that activity,
and the project completion time calculated in part 4 is the expected completion time for the
project and also project variance is 10 weeks. What is the probability of finishing the
project within a range of 3 weeks earlier than the expected completion time and 1 week
later? Additionally, what is the probability of finishing the project 4 or more weeks beyond
the expected completion time? Lastly, what due date would yield a 75% chance of
completion?
9. Suppose that project indirect costs are $7,000 per week. Suppose also that, after week 25,
a penalty cost of $22,000 per week if the project is not fully completed. For every week
that the project is shortenedto week 25the Hard Rock Cafe saves one week of penalty
and indirect costs. For reductions beyond week 25, the savings are only the weekly indirect
costs. Determine the minimum-cost schedule for the Rockfest concert project. The goal
here is to determine how much you can add in crash costs without exceeding the savings
in indirect and penalty costs. In accordance with Hard Rock Cafe's standard procedures,
you are required to create an executive summary aimed at your project manager. The
purpose of this summary is to persuasively present your recommendations from question
6 and convince the manager to consider them (you can use graph to support your
recommendations). The document must be of professional quality in both content and
format and must clearly outline each step taken in determining the minimum-cost schedule.
Activity Description Predecessor(s)
Normal
Time
Normal
Cost
Crash
time
Crash
Cost
A Finalize site and building contracts -7120000041236000
B Select local promoter A 3400024600
C Hire production manager A 350000257000
D Design promotional Web site B 4500026000
E Set TV deal D, K 616000518000
F Hire director E 41200003128000
G Plan for TV camera placement F 210000111500
H Target headline entertainers B 412000313000
I Target support entertainers H 440000342500
J Travel accommodations for talent I 125000009509000
K Set venue capacity C 310000140000
L Ticketmaster contract D, K 330000234000
M On-site ticketing L 18130001017000
N Sound and staging C 610000413000
O Passes and stage credentials G, R 5400035200
P Travel accommodations for staff B 22500001599000
Q Hire sponsor coordinator B 410000213000
R Finalize sponsors Q 412000313000
S Define/place signage for sponsors R, X 340000250000
T Hire operations manager A 41400003150000
U Develop site plan T 6900005100000
V Hire security director T 750000564000
W Set police/fire security plan V 410000212000
X Power, plumbing, toilet services U 840000652000
Y Secure merchandise deals B 6400054500
Z Online merchandise sales Y 6500055500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!