Question: A project network is shown below. Activity Precedence Activities Optimistic Most Probable Pessimistic Time (weeks) A -- 1 5 10 B -- 2 4 8
A project network is shown below.
|
Activity | Precedence Activities | Optimistic Most Probable Pessimistic Time (weeks) |
| A | -- | 1 5 10 |
| B | -- | 2 4 8 |
| C | -- | 4 8 12 |
| D | A, B | 2 4 8 |
| E | C | 10 12 14 |
| F | C | 4 10 16 |
| G | D, E | 1 3 5 |
| H | E | 1 2 3 |
| I | E, F | 2 5 7 |
- What is the expected completion time and variance for activity C?
| A. | Expected completion time = 12, Variance = 1.333 | |
| B. | Expected completion time = 8, Variance = 1.333 | |
| C. | Expected completion time = 8, Variance = 1.778 | |
| D. | Expected completion time = 4, Variance = 1.778 |