Question: Assume this project is time - constrained ( it has a non - negotiable due date ) . As project manager, what should you do

Assume this project is time-constrained (it has a non-negotiable due date). As project manager, what should you do if it looks as though Activity #5 is going to finish two days late?
Apply the resource smoothing technique.
Notify the project sponsor that the project will be late.
Do nothing for now because Activity 5 is NOT on the critical path, but continue to monitor the situation to make sure Activity 5 does not get delayed any further.
Add resources (such as hire additional workers or pay current employees overtime) to expedite this activity.
 Assume this project is time-constrained (it has a non-negotiable due date).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!