Question: Assume this project is time - constrained ( it has a non - negotiable due date ) . As project manager, what should you do
Assume this project is timeconstrained it has a nonnegotiable due date As project manager, what should you do if it looks as though Activity # is going to finish two days late?
Apply the resource smoothing technique.
Notify the project sponsor that the project will be late.
Do nothing for now because Activity is NOT on the critical path, but continue to monitor the situation to make sure Activity does not get delayed any further.
Add resources such as hire additional workers or pay current employees overtime to expedite this activity.