Assume we're halfway through a year-long project that has a total budget of 300000 AED. The...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Assume we're halfway through a year-long project that has a total budget of 300000 AED. The amount budgeted through this six-month mark is 205000 AED and a total of 190000 AED spent. Calculate the following: a) Budget at Completion (BAC) Budget at Completion (BAC) = Answer AED b) Planned Value (PV) c) Actual Cost (AC) Planned Value (PV) = Answer AED Actual Cost (AC) = Answer d) Earned Value (EV) Earned Value (EV) = Answer e) Cost Variance (CV) Cost Variance (CV) = Answer 205000 f) Schedule Variance (SV) 102500 Answer PV to date * Rate of performance (RP) 300000*(6/12) or 50% Schedule Variance (SV) = Answer EV-AC 102500 EV-PV g) Schedule Performance Index (SPI) Schedule Performance Index (SPI) = Answer EV/PV 205000 h) Cost Performance Index (CPI) Cost Performance Index (CPI) = Answer EV/AC 190000 300000 50% 190000 Answerl = Answer. 102500 102500 Answerl AED Answer 205000 102500 /Answer 205000 Answer /Answer 190000 -87500 AED AED -10250 AED =Answer 0.5 Answerl 0.53 1) Estimated at Completion (EAC) 300000 0.53 Estimated at Completion (EAC) = Answer! / Answer = Answerl BAC/CPI 1) Estimated Time to compete Time to compete = Answer ¹2/Answer 05 Because SV is Answer behind the schedule Total months * SPI The project manager must determine how well his project team has performed. Is he ahead of schedule or behind schedule, and is the project team over or under budget? Answer the following: positive Because CV is Answer under-budgeted k) The project is considered behind the schedule, is ahead of schedule, or is as per schedule. and Answer positive and Answer Answer SPI 1 Please answer all parts of the question. 568037 1) The project is considered over-budgeted, is under-budgeted, or is as budgeted. Months CPK1 AED , the project is Answer , the project is Answer Assume we're halfway through a year-long project that has a total budget of 300000 AED. The amount budgeted through this six-month mark is 205000 AED and a total of 190000 AED spent. Calculate the following: a) Budget at Completion (BAC) Budget at Completion (BAC) = Answer AED b) Planned Value (PV) c) Actual Cost (AC) Planned Value (PV) = Answer AED Actual Cost (AC) = Answer d) Earned Value (EV) Earned Value (EV) = Answer e) Cost Variance (CV) Cost Variance (CV) = Answer 205000 f) Schedule Variance (SV) 102500 Answer PV to date * Rate of performance (RP) 300000*(6/12) or 50% Schedule Variance (SV) = Answer EV-AC 102500 EV-PV g) Schedule Performance Index (SPI) Schedule Performance Index (SPI) = Answer EV/PV 205000 h) Cost Performance Index (CPI) Cost Performance Index (CPI) = Answer EV/AC 190000 300000 50% 190000 Answerl = Answer. 102500 102500 Answerl AED Answer 205000 102500 /Answer 205000 Answer /Answer 190000 -87500 AED AED -10250 AED =Answer 0.5 Answerl 0.53 1) Estimated at Completion (EAC) 300000 0.53 Estimated at Completion (EAC) = Answer! / Answer = Answerl BAC/CPI 1) Estimated Time to compete Time to compete = Answer ¹2/Answer 05 Because SV is Answer behind the schedule Total months * SPI The project manager must determine how well his project team has performed. Is he ahead of schedule or behind schedule, and is the project team over or under budget? Answer the following: positive Because CV is Answer under-budgeted k) The project is considered behind the schedule, is ahead of schedule, or is as per schedule. and Answer positive and Answer Answer SPI 1 Please answer all parts of the question. 568037 1) The project is considered over-budgeted, is under-budgeted, or is as budgeted. Months CPK1 AED , the project is Answer , the project is Answer
Expert Answer:
Answer rating: 100% (QA)
a Budget at Completion BAC 300000 AED b Planned Value PV 205000 AED c Actual Cost AC 190000 AED d Earned Value EV PV to date Rate of performance RP 205000 05 102500 AED e Cost Variance CV EV AC 102500 ... View the full answer
Related Book For
Horngrens Financial and Managerial Accounting
ISBN: 978-0133866292
5th edition
Authors: Tracie L. Nobles, Brenda L. Mattison, Ella Mae Matsumura
Posted Date:
Students also viewed these accounting questions
-
Assume that SSC has a $112.5 million capital budget planned for the coming year. You have determined its present capital structure (80% equity and 20% debt) is optimal, and its net income is...
-
A consulting project has an actual cost in month 10 of $23,000, a scheduled cost of $17,000, and a value completed of $20,000. Find the schedule and cost variances and the three indexes.
-
A performance report that compares budgeted and actual profit in the sporting goods department of Maxwells Department Store for the month of December follows: Required a. Evaluate the department in...
-
A factory with three departments uses a single production overhead absorption rate expressed as a percentage of direct wages cost. It has been suggested that departmental overhead absorption rates...
-
How did the environment of the American Fur Company change in the 1830s? What deep historical forces are implicated in these changes?
-
Rockland Shoe Company records Sales Returns and Allowances, Sales Discounts, and Credit Card Discounts as contra-revenues. Complete the following tabulation, indicating the effect (+ for increase,...
-
Explain how the control variate technique is implemented.
-
Zap Rap Inc. is a manufacturer of audio CDs. The companys chief financial officer is trying to verify the accuracy of the December 31 work in process and finished goods inventories prior to closing...
-
2.1 Design and determine data storage requirements from NoSQL data store according to selected vendor technology and business requirements
-
Potts, Inc., recently converted from a 5-day, 40-hour workweek to a 4-day, 40-hour workweek, with overtime continuing to be paid at one and one-half times the regular hourly rate for all hours worked...
-
Choose the correct answer. What is the unit rate of 300km in 5 hours? a. 25m per hour b. 50km per minute c. 125km per 2 hours d. 60km per hour
-
Determine the stresses at points A and B as a results of applying each of the following internal loads N = 300 N, V = 250 N, M = 120 N.m and T = 300 N/m. The diameter is 20 mm. You must show your...
-
Using Exponential form. The phase shift between two systems has been expressed as: 2 <120 + 5.2 <58 -1.6 < -40. The correction to this phase shift is expressed as (-1-5j).
-
Calculate the moment of inertia of the shape about the indicated axis In the horizontal direction, assume the centroid is located in the midide of shape 1.00 6.00 3.50 3.50 3.00 Z 1.00 1 (2) 2.00 (3)...
-
1. The parabolic function in the figure represents the profile of the water flow velocity between two plates placed 0.01 m apart. In the velocity formula, y is expressed in meters. Calculate the...
-
2. The transducer specified in Table 1.1 (below) is chosen to measure a nominal pressure of 700 cm HO. The ambient temperature is expected to vary between 20C and 25C during tests. Determine each...
-
3. Suppose all government bonds have par value of $1000. There is only 1-year zero bond in the market. The 2-year coupon bond and the 3-year coupon bond pay at the same coupon rate of 8%. Price...
-
Coastal Refining Company operates a refinery with a distillation capacity of 12,000 barrels per day. As a new member of Coastal's management team, you have been given the task of developing a...
-
Journalize issuance of the bond and the first semiannual interest payment under each of the following three assumptions. The company amortizes bond premium and discount by the effective-interest...
-
Arkansas Sales Consultants completed the following transactions during the latter part of January: Jan. 22 Performed services for customers on account, $9,000. 30 Received cash on account from...
-
Winterborn Manufacturing Co. completed the following transactions during 2016: Jan. 16 Declared a cash dividend on the 4%, $100 par noncumulative preferred stock (950 shares outstanding). Declared a...
-
Find the frequency response of the given system. \(4 \ddot{x}+12 \dot{x}+13 x=40 \sin \left(\frac{1}{3} t ight)\)
-
A second-order dynamic system is modeled as \[4 \ddot{x}+4 \dot{x}+5 x=0, \quad x(0)=0.4, \dot{x}(0)=0\] a. Find the free response \(x(t)\). b. \(A\) Plot the free response by using the initial...
-
Plot the specified output by using the RK4 method. \(4 \ddot{x}+3 \dot{x}+2 x|x|=\frac{1}{2}+\sin t, \quad x(0)=1, \quad \dot{x}(0)=-1, \quad 0 \leq t \leq 15\), output : \(x\)
Study smarter with the SolutionInn App