Question: Assume you are the Project Manager for a new software development project. One of your project team members tells you that the project is a

Assume you are the Project Manager for a new software development project. One of your project team members tells you that the project is a super success because the project was supposed to be done in 10 weeks with total budget of CA$ 90,000. Now, project team is at the end of Week 6 and they have spent CA$ 65,000 and 40% of project is remained.
A) Canulate CV and SV for this project. Show all you calculation [2 marks]