Question: Assume you are the Project Manager for a new software development project. According to approved schedule, project is supposed to be finished in 10 weeks.
Assume you are the Project Manager for a new software development project. According to approved schedule, project is supposed to be finished in 10 weeks. The status report at the end of the 6th week says the project has a CPI of 0.85 and an SPI of 1.20. A) Is the project on track? Ensure you refer to both the budget and the schedule based on the provided values for CPI and SPI. [2 Marks] B) Share one recommendation to get the project back on track. (Interpretation and recommendation). [1 mark]