Question: Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your companys database

Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your companys database indicates that developers can handle eight function points each person-month and that the cost per developer at your firm is $8,200 per month. You and your team of five developers have come up with the following requirements:

Elements

Count

Complexity

Inputs

26

Low

Outputs

20

Low

Inquiries

20

High

Files

44

Medium

Interfaces

34

High

Calculate the total number of function points, the estimated cost, and the duration of the Tidal project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!