Question: Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your companys database
Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your companys database indicates that developers can handle eight function points each person-month and that the cost per developer at your firm is $8,200 per month. You and your team of five developers have come up with the following requirements:
| Elements |
| Count |
| Complexity |
| Inputs |
| 26 |
| Low |
| Outputs |
| 20 |
| Low |
| Inquiries |
| 20 |
| High |
| Files |
| 44 |
| Medium |
| Interfaces |
| 34 |
| High |
Calculate the total number of function points, the estimated cost, and the duration of the Tidal project.