Assume you are the project manager of a project. The planned schedule is as follows. Each phase
Fantastic news! We've Found the answer you've been seeking!
Question:
- Assume you are the project manager of a project. The planned schedule is as follows. Each phase is planned to be completed one after the other. Today is the end of June.
Task | Scheduled | Duration | Budget |
Project Planning | January | 1 month | $8, 000 |
Requirement | February and March | 2 months | $16, 000 |
Design | April | 1 month | $10, 000 |
Coding | May and June | 2 months | $22, 000 |
Testing | July and August | 2 months | $20, 000 |
(1) use the project status chart, calculate the following values.
At the end of June,
Task | Status at the end of June |
Project Planning | Complete, spent $5,000 |
Requirement | Complete, spent $14,000 |
Design | Complete, spent $12,000 |
Coding | 50% Complete, spent $12,000 |
Testing | Not yet started |
Value | Show the calculation | Answer |
PV(BCWS) | ||
EV(BCWP) | ||
AC(ACWP) |
(2) Describe the current budget and schedule situation (e.g. over budget? behind schedule?).
Budget:
Schedule: