Question: assuming a process is in statistical process control with an Xbar chart of .85 and an average range of .02. Assume subgroups to be 6.
assuming a process is in statistical process control with an Xbar chart of .85 and an average range of .02. Assume subgroups to be 6. Assume engineering specifications to be .85 +/- .015. What is the process standard deviation, Z Lower, Z Higher, Cp, Cr, Cm, ZMin, and Cpm? Comment on each of these process capability metrics as they relate to the process meeting the engineering specifications