Question: Assuming that an expected project completion time follows the normal probability distribution with a mean of 200 days and standard deviation of 50 days. What
Assuming that an expected project completion time follows the normal probability distribution with a mean of 200 days and standard deviation of 50 days. What is the probability that the project will be completed within 169.96 days or more?
A. 1.726
B.0.726
C.1.274
D.None
E.0.274