Question: Assuming the contract was main Option A and the Project Manager had received a proposal from the Contractor to change the Scope reducing the amount

Assuming the contract was main Option A and the Project Manager had received a proposal from the Contractor to change the Scope reducing the amount paid to the Contractor by the Client, which TWO of the following statements are correct?
Select TWO options
A change to the Scope is a compensation event which could lead to an earlier Completion Date
The value engineering percentage is applied to the assessed value of the compensation event
The compensation event would not lead to a reduction in the Prices
The Contractor is only permitted to make proposals to change the Scope provided by the Client if secondary Option X22 is included in the contract
The Project Manager should respond to the Contractor within four weeks of the proposal

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!