Question: Assuming the following standard times for 5 different sequential operations in a simple assembly line, (a) compute the efficiency of this assembly process, and (b)
Assuming the following standard times for 5 different sequential operations in a simple assembly line, (a) compute the efficiency of this assembly process, and (b) determine how many pieces will be produced by this process in an 8-hour day.
Operation 1: ST = 1.32 minutes
Operation 2: ST = 1.45 minutes
Operation 3: ST = 1.15 minutes
Operation 4: ST = 1.20 minutes
Operation 5: ST = 1.18 minutes