Question: Assuming the MPS quantity is 80 & no customer orders beyond week 3 , what is the projected onhand inventory in week two? 1 4
Assuming the MPS quantity is 80 \& no customer orders beyond week 3 , what is the projected onhand inventory in week two? 1 4 12 21 43