Question: Assuming the projects below are all mutually exclusive, which one would you recommend undertaking purely on grounds of the project's anticipated financial value? Project 1
Assuming the projects below are all mutually exclusive, which one would you recommend undertaking purely on grounds of the project's anticipated financial value? Project 1 NPV: \\( \\$ 5,000 \\) IRR: \45 Project 2 NPV: \\( \\$ 4,500 \\) IRR: \75 Project 3 NPV: \\$2,000 IRR: \60 A) Project 1 B) Project 2 C) Project 3 D) The answer cannot be determined from the information given